ASPICE MAN.3 Project Management
Get Started with This SkillOverview
Elaborate ASPICE MAN.3 work products: project plan, monitoring data, and corrective actions for Automotive SPICE (VDA PAM 4.0).
Getting Started
Add your source materials to the project workspace, then activate the ASPICE MAN.3 Project Management skill. The agent will guide you through the process step by step.
Example Conversation
You: We need to document our project plan and monitoring for MAN.3 ahead of an ASPICE assessment. We have a schedule in Jira and a risk register in a spreadsheet.
Agent: I’ll help you elaborate MAN.3 work products. I need: (1) Project scope — deliverables and work breakdown (e.g. SYS/SWE work products); (2) Schedule — milestones and key activities; (3) Resources — roles and effort; (4) Risks — from your register; (5) How you currently track status (e.g. weekly report, dashboard). I can draft the project plan and a monitoring template.
You: Scope is the ECU project through SYS.5 and SWE.5. Milestones are baseline dates from our Gantt. We have 3 risks in the register. We do weekly status.
Agent: I’ve created
project-plan.mdwith scope (deliverables and WBS), schedule (milestones and key activities), resources (roles and effort), risks (three with mitigation), and quality objectives. I’ve addedproject-status-template.mdfor weekly monitoring: progress vs plan, effort, issues, risks. When you have a deviation and take corrective action, record it incorrective-actions.md(what, who, when, decision). I can plug in your next milestone dates from the Gantt if you share them.
Sample Output Excerpt
Below is a representative excerpt from MAN.3 project plan and monitoring work products.
Project plan (excerpt)
| Section | Content |
|---|---|
| Scope | ECU project; deliverables: SYS.1–SYS.5, SWE.1–SWE.5 work products; integration and qualification. |
| Milestones | M1: Requirements baseline (Mar); M2: Design baseline (Jun); M3: Integration complete (Sep); M4: Qualification complete (Nov). |
| Risks | R1: Radar supplier delay — mitigation: dual source evaluation. R2: Tool chain upgrade — mitigation: pilot in Q2. |
Corrective actions (excerpt)
| ID | Date | Deviation | Action | Owner |
|---|---|---|---|---|
| CA-001 | 2025-02-10 | SYS.4 integration 1 week behind | Extra HIL slot allocated; daily sync with test team | Project manager |
Validation
This skill does not include extension tools. Validation is performed by following the Validation checklist in the skill workflow: project plan covers scope, schedule, resources, risks, and quality; monitoring data is recorded regularly; corrective actions are documented when deviations occur; plan updates are baselined and communicated.