Browse Skills

PMBOK Cost Management

    Get Started with This Skill

    Overview

    The PMBOK Cost Management skill supports the elaboration of documents for the Cost Management knowledge area — planning, estimating, budgeting, financing, and controlling costs so the project is completed within the approved budget. It covers cost management plans defining estimation methodology and EVM rules, cost estimates using analogous, parametric, bottom-up, or three-point techniques, basis of estimates documenting assumptions and confidence levels, project budgets with contingency and management reserves, time-phased cost baselines, and Earned Value Management performance reports with full metric calculations (PV, EV, AC, CV, SV, CPI, SPI, EAC, ETC, VAC, TCPI).

    Getting Started

    Upload your WBS, resource rates, or vendor quotes to the workspace and activate the PMBOK Cost Management skill. The agent will ask about the estimation technique, currency, and reserve policies, then build estimates tied to WBS work packages. For Earned Value reporting, provide current PV, EV, and AC data — the agent calculates all metrics, shows formulas, interprets trends, and recommends corrective actions.


    Example Conversation

    Below is an example of a typical session producing an Earned Value cost performance report at the midpoint of a software project.

    You: I need a cost performance report for our mobile app project at the end of Month 6 (of 12). Here’s the data: BAC = $1,200,000. Planned Value (cumulative): $620,000. Earned Value (cumulative): $540,000. Actual Cost (cumulative): $610,000. We’ve completed 45% of the work. Can you calculate all EVM metrics and tell me what’s going on?

    Agent: Here’s the Earned Value analysis for Month 6:

    Variances:

    • CV = EV - AC = $540,000 - $610,000 = -$70,000 (over budget)
    • SV = EV - PV = $540,000 - $620,000 = -$80,000 (behind schedule)

    Performance Indices:

    • CPI = EV / AC = $540,000 / $610,000 = 0.89 (spending $1.13 for every $1 of value earned)
    • SPI = EV / PV = $540,000 / $620,000 = 0.87 (progressing at 87% of planned rate)

    Forecasts:

    • EAC (typical) = BAC / CPI = $1,200,000 / 0.89 = $1,348,315
    • EAC (atypical) = AC + (BAC - EV) = $610,000 + $660,000 = $1,270,000
    • ETC = EAC - AC = $738,315 (if current performance continues)
    • VAC = BAC - EAC = -$148,315
    • TCPI (to meet BAC) = (BAC - EV) / (BAC - AC) = $660,000 / $590,000 = 1.12

    Interpretation: The project is both over budget and behind schedule. With a TCPI of 1.12, you would need to perform the remaining work at 112% cost efficiency — a significant improvement over current performance. I recommend three corrective actions: (1) root-cause analysis of the cost variance, (2) evaluate scope reduction or fast-tracking opportunities, and (3) consider requesting a revised budget (EAC) of $1,350,000 with justification to the Change Control Board.

    The full report with formulas, trend charts description, and corrective action plan is saved.


    Document Excerpt

    Below is a representative excerpt from an Earned Value cost performance report drafted with the skill.


    Cost Performance Report — Excerpt

    Project: Mobile Banking App v2.0 Reporting Period: Month 6 of 12 Currency: USD


    Earned Value Summary

    MetricFormulaValueStatus
    Budget at Completion (BAC)$1,200,000Baseline
    Planned Value (PV)Cumulative planned spend$620,000
    Earned Value (EV)% complete × BAC$540,000
    Actual Cost (AC)Cumulative actual spend$610,000

    Variance Analysis

    MetricFormulaValueInterpretation
    Cost Variance (CV)EV - AC-$70,000Over budget by $70K
    Schedule Variance (SV)EV - PV-$80,000Behind schedule by $80K worth of work
    Cost Performance Index (CPI)EV / AC0.89Earning $0.89 per $1 spent
    Schedule Performance Index (SPI)EV / PV0.87Completing 87% of planned work per period

    Forecasts

    ForecastFormulaValueAssumption
    EAC (typical)BAC / CPI$1,348,315Current cost performance continues
    EAC (atypical)AC + (BAC - EV)$1,270,000Variance was one-time; future work at planned rate
    EAC (combined)AC + (BAC - EV) / (CPI × SPI)$1,461,872Both cost and schedule trends continue
    ETCEAC - AC$738,315Based on typical EAC
    VACBAC - EAC-$148,315Expected budget overrun
    TCPI (BAC)(BAC - EV) / (BAC - AC)1.12Required efficiency to finish within BAC

    Corrective Actions

    #ActionOwnerDeadlineExpected Impact
    1Conduct root-cause analysis of $70K cost overrun — focus on contractor overtime in Sprint 4–6PM / FinanceWeek 26Identify whether overrun is systemic or isolated
    2Re-negotiate contractor rates or reduce scope of non-critical features (push notifications, analytics dashboard)PM / SponsorWeek 27Potential savings of $80K–$120K
    3Submit EAC revision ($1,350,000) to Change Control Board with trend analysisPMWeek 28Formal budget re-baseline if approved

    This excerpt is illustrative. Final content must reflect the specific project’s financial data, organizational policies, and current EVM standards.

    Ready to let your expertise drive the workflow?

    Stop wrestling with rigid templates and complex tooling. Write your process in markdown, let the agent handle the rest.

    Get Started