The PMBOK Schedule Management skill supports the elaboration of documents for the Schedule Management knowledge area — establishing the policies, procedures, and documentation for planning, developing, managing, and controlling the project schedule. It covers schedule management plans, activity lists derived from WBS work packages, milestone lists, activity sequencing with precedence relationships (FS, FF, SS, SF with leads and lags), three-point duration estimates using PERT, schedule baselines with critical path identification, and schedule performance reports using Earned Value metrics (SPI, SV, EAC forecasting).
Getting Started
Upload your WBS or deliverables list to the workspace and activate the PMBOK Schedule Management skill. The agent will ask about the scheduling methodology (CPM, Critical Chain, Agile iterations, or hybrid), calendar constraints, and estimation technique preference. It then decomposes work packages into activities, sequences them, estimates durations, identifies the critical path, and produces the schedule baseline. For monitoring, provide current EV data to get a performance report with variance analysis and corrective action recommendations.
Example Conversation
Below is an example of a typical session building duration estimates and identifying the critical path for a construction project.
You: I need three-point duration estimates for our office renovation project. We have the activity list ready — 12 activities from demolition through final inspection. I want PERT estimates and the critical path identified. The activities and their predecessors are in
schedule/activity_list.md.Agent: I’ve read your activity list. I’ll produce three-point estimates using the PERT formula (O + 4M + P) / 6. For each activity, I need your best assessment of optimistic, most likely, and pessimistic durations. Do you want to provide these, or should I propose initial estimates based on typical office renovation benchmarks that you can then adjust?
You: Propose initial estimates and I’ll adjust. Standard 500 sqm office space, concrete structure, no structural changes.
Agent: Here are the proposed estimates. I’ve also sequenced the activities, calculated the critical path, and identified float for each activity. Key findings:
- Critical path: Demolition → Electrical Rough-In → HVAC Installation → Drywall → Painting → Flooring → Final Inspection — total 48.3 working days (PERT)
- Near-critical path: Plumbing Rough-In runs parallel with only 2.2 days of float
- Project PERT duration: 48.3 days with a standard deviation of 4.1 days
- At P90 confidence, the project would take approximately 53.6 days
The full estimate table, sequencing diagram, and critical path analysis are saved in
output/schedule_estimates.md. Please review the optimistic/pessimistic ranges — I’ve noted two activities where the spread is unusually wide and may warrant further investigation.
Document Excerpt
Below is a representative excerpt from a PERT estimate table with critical path analysis drafted with the skill.
Duration Estimates & Critical Path — Excerpt
Project: Office Renovation — Building C, Floor 3 Methodology: CPM with PERT three-point estimates Calendar: 5-day work week, 8 hours/day
Duration Estimates
| ID | Activity | Predecessors | Type | Optimistic (days) | Most Likely (days) | Pessimistic (days) | PERT Estimate | Std Dev |
|---|---|---|---|---|---|---|---|---|
| A1 | Demolition & Strip-Out | — | — | 3 | 5 | 10 | 5.5 | 1.17 |
| A2 | Electrical Rough-In | A1 | FS | 4 | 6 | 10 | 6.3 | 1.00 |
| A3 | Plumbing Rough-In | A1 | FS | 3 | 5 | 9 | 5.3 | 1.00 |
| A4 | HVAC Installation | A2 | FS | 5 | 7 | 12 | 7.5 | 1.17 |
| A5 | Fire Protection | A2, A3 | FS | 2 | 3 | 5 | 3.2 | 0.50 |
| A6 | Drywall & Framing | A4, A5 | FS | 4 | 6 | 9 | 6.2 | 0.83 |
| A7 | Painting | A6 | FS | 3 | 4 | 7 | 4.3 | 0.67 |
| A8 | Flooring | A7 | FS | 4 | 5 | 8 | 5.3 | 0.67 |
| A9 | Ceiling & Lighting | A6 | FS | 3 | 4 | 6 | 4.2 | 0.50 |
| A10 | Furniture & Fixtures | A8, A9 | FS | 2 | 3 | 5 | 3.2 | 0.50 |
| A11 | IT & AV Installation | A9 | FS | 3 | 4 | 7 | 4.3 | 0.67 |
| A12 | Final Inspection | A10, A11 | FS | 1 | 2 | 3 | 2.0 | 0.33 |
Critical Path
| Sequence | Activity | PERT Duration | Cumulative | Float |
|---|---|---|---|---|
| 1 | A1 — Demolition & Strip-Out | 5.5 | 5.5 | 0.0 |
| 2 | A2 — Electrical Rough-In | 6.3 | 11.8 | 0.0 |
| 3 | A4 — HVAC Installation | 7.5 | 19.3 | 0.0 |
| 4 | A6 — Drywall & Framing | 6.2 | 25.5 | 0.0 |
| 5 | A7 — Painting | 4.3 | 29.8 | 0.0 |
| 6 | A8 — Flooring | 5.3 | 35.1 | 0.0 |
| 7 | A10 — Furniture & Fixtures | 3.2 | 38.3 | 0.0 |
| 8 | A12 — Final Inspection | 2.0 | 40.3 | 0.0 |
Critical path duration: 40.3 working days (PERT) Project standard deviation: 2.1 days P90 estimate: 40.3 + (1.28 × 2.1) = 43.0 working days
This excerpt is illustrative. Final content must reflect the specific project’s activities, durations, and sequencing logic.