Browse Skills

PRINCE2 Directing a Project

    Get Started with This Skill

    Overview

    Draft Directing a Project (DP) documents aligned with PRINCE2. Covers Project Board authorization decisions, ad hoc direction, exception handling, stage gate approvals, and project closure authorization.

    Getting Started

    Upload the relevant End Stage Report, Exception Report, or project status materials to the workspace and activate the PRINCE2 Directing a Project skill. The agent will help you draft Board-level authorization decisions, exception responses, and governance documentation.


    Example Conversation

    Below is an example of a typical session preparing a Stage Authorization Decision for a Project Board meeting. The agent reviews stage performance and drafts the Board’s decision record.

    You: We’re at the end of Stage 2 (pilot phase) of our ERP implementation. The pilot ran 2 weeks over schedule but came in EUR 15K under budget. All 3 pilot products were delivered and accepted. I need to prepare the Stage Authorization Decision for the Board to approve Stage 3 (full rollout). The End Stage Report is in reports/end_stage_2.md.

    Agent: I’ve reviewed the End Stage Report. Let me draft the Stage Authorization Decision. A few questions:

    1. What tolerances do you want to propose for Stage 3? The project-level tolerances are +/- 10% cost, +/- 4 weeks schedule.
    2. Are there any risks from the pilot that the Board should consider before approving rollout?
    3. Has the Business Case been updated to reflect the pilot results?

    You: Proposed Stage 3 tolerances: +/- EUR 50K cost, +/- 3 weeks schedule, scope tolerance of one deferred module. Main risk from the pilot: data migration took 40% longer than estimated — we need to factor that into the rollout plan. Business Case is updated: ROI improved slightly because pilot licensing costs were lower than expected.

    Agent: I’ve drafted the Stage Authorization Decision covering all Board perspectives. Here’s a summary:

    • Stage 2 Review — schedule overrun of 2 weeks (within project tolerance), cost underrun of EUR 15K, all products accepted, one lesson on data migration estimation
    • Business Case Review — still justified, ROI improved from 1.8x to 1.9x due to lower licensing costs
    • Risk Assessment — data migration risk upgraded to High with revised estimates built into Stage 3 plan; overall risk exposure acceptable
    • Stage 3 Plan Assessment — 14-week rollout, EUR 280K budget, all 3 departments, revised data migration timeline
    • Tolerances Set — cost: +/- EUR 50K, schedule: +/- 3 weeks, scope: one module deferral permitted
    • Decision — recommend: Authorize Stage 3

    The draft is saved as decisions/stage_3_authorization.md. The Board members section has placeholders for names and the decision date.


    Document Excerpt

    Below is a representative excerpt from a Stage Authorization Decision prepared with the skill.


    Stage Authorization Decision — ERP Implementation Stage 3 (Excerpt)

    Project: Enterprise Resource Planning Implementation Decision Point: End of Stage 2 / Authorization of Stage 3


    1. Stage Under Review — Stage 2 (Pilot)

    DimensionPlannedActualVarianceWithin Tolerance?
    Duration8 weeks10 weeks+2 weeksYes (project tolerance: +/- 4 weeks)
    CostEUR 95,000EUR 80,000-EUR 15,000Yes
    Products3 delivered3 delivered and acceptedOn targetYes
    QualityAll reviews passed2 conditional passes resolvedAcceptableYes

    Key Finding: Data migration activities took 40% longer than estimated. Root cause: legacy data quality issues required additional cleansing. Lesson applied to Stage 3 estimates.

    3. Business Case Review

    MetricAt PIDCurrent (updated)Change
    Total project costEUR 520,000EUR 505,000-EUR 15,000
    3-year net benefitEUR 420,000EUR 445,000+EUR 25,000
    ROI1.8x1.9xImproved
    Payback period22 months21 monthsImproved

    Conclusion: Project remains justified. Benefits case has strengthened.

    5. Decision

    ItemDetail
    DecisionAuthorize Stage 3 (Full Rollout)
    ConditionsData migration estimates must include 40% buffer based on pilot learning. Stage 3 plan to be updated before work begins.
    Stage 3 TolerancesCost: +/- EUR 50,000. Schedule: +/- 3 weeks. Scope: one module may be deferred to post-project.
    Board MemberRoleSignatureDate
    [Executive name]Executive__________________
    [Senior User name]Senior User__________________
    [Senior Supplier name]Senior Supplier__________________

    This excerpt is illustrative. Final content must reflect the specific project’s data and governance context.

    Ready to let your expertise drive the workflow?

    Stop wrestling with rigid templates and complex tooling. Write your process in markdown, let the agent handle the rest.

    Get Started